East Coast Offshore Wind Projects Take Giant Steps | 2019-09-20 ...

By Shawn Soper Ocean City (Md) Dispatch

OCEAN CITY — Independent stakeholders in one of two offshore wind projects appear to have little concern with the significantly larger turbines selected, according to briefs filed with the Maryland Public Service Commission following a hearing last month.

In June, the Maryland Public Service Commission (PSC) held an evidentiary hearing on the proposed change in wind turbine size for Orsted’s Skipjack project off the coast of Ocean City. The evidentiary hearing was called when Skipjack announced its intention to switch from the previously proposed eight-megawatt turbines to the much larger 12-megawatt turbine, now believed to be the largest commercial wind turbine available.

Don’t miss stories like this Click for free EnviroPolitics Blog updates

When Skipjack moved to the 12-megawatt turbine, the Town of Ocean City urged the PSC to hold an evidentiary hearing on the proposed turbine change. After a well-attended public hearing in Ocean City in January, the PSC agreed to hold the evidentiary hearing and it took place virtually in early June.

Last week, several weeks after that evidentiary hearing, the interested and participating parties filed post-hearing briefs with the PSC outlining their positions on the issues at hand. Naturally, the Town of Ocean City and Skipjack stuck to their long-held positions, but perhaps the most interesting conclusions came in the briefs filed by neutral third parties. For example, in its brief filed last week, the staff of the PSC agreed with Skipjack’s contention moving to the larger turbines will result in fewer turbines moved further out in the approved Wind Energy Area (WEA).

“The decision to increase the size of the wind turbines from eight megawatts to 12 megawatts will reduce the number of wind turbines needed for the 120-megawatt project from 15 to 12 or fewer turbines,” the brief reads. “By reducing the number of turbines, the distance from the Maryland shoreline to the nearest turbine could be increased from 19.5 miles to 22.7 miles.”

In its brief, the PSC concluded despite the proposed change in turbine height, the Skipjack project still met the standards laid out in the state’s legislation approved seven years ago.

“The increase in wind turbine size thus is not only consistent with the Maryland Offshore Wind Energy Act of 2013, but it would also reduce the impact upon the environment and should reduce total costs of the project to Maryland ratepayers,” the brief reads.

Read the full story